Planning – Planning Application Documents

Help with this page (opens in a new window)

14/03201/RES | Details of reserved matters (layout, scale, appearance and landscaping) for a scheme of Enabling Infrastructure Works (such as utility services, earthworks, drainage/attenuation and roadworks), pursuant to conditions 3 and 4 of the outline planning permission for the mainly residential development of the site (13/01383/OUT). More specifically these works comprise:- a) the primary street, street furniture, on-street parking, street lighting, surface water drainage swales, associated landscaping and surface finishes; b) green infrastructure, the linear park, greenways, hard and soft landscaping, footpaths, cycle paths and ecological improvements; c) landscaping details for the approved A40 junction; d) buried services and utilities, foul and surface water drainage, water channels, ponds, sustainable urban drainage systems and underground storage tanks. This reserved matters application (14/03201/RES) is accompanied by the following additional submissions in relation to conditions and non-material amendments to the above mentioned outline permission:- i) condition 11 - tree protection (13/01383/CND2); ii) conditions 24 - site-wide surface water drainage scheme (13/01383/CND3); iii) condition 25 - enabling infrastructure phased surface water drainage system (13/01383/CND2); iv) condition 26 - site-wide foul water drainage strategy (13/01383/CND3); and, v) non-material amendments to approved A40 junction e.g. omission of splitter island (13/01383/NMA). | Land West Of Barton North Of A40 And South Of Bayswater Brook Northern By-pass Road Wolvercote Oxfordshire OX3 9SD

You can select up to 25 documents to download in one archive file at a time.

Date Published Document Type Measure Description View
10 Jun 2016 Decision Measure document icon Decision letter - amendment View document icon
10 Jun 2016 Drawing Measure document icon Kerb detailing amendment View document icon
27 Oct 2015 Decision Measure document icon Decision letter - amendment View document icon
22 Oct 2015 Public Correspondence Measure document icon Highways comments View document icon
29 Sep 2015 Drawing Measure document icon Primary street general arrangement plan 1 of 3 View document icon
29 Sep 2015 Drawing Measure document icon Primary street general arrangement plan 2 of 3 View document icon
29 Sep 2015 Drawing Measure document icon Primary street hardworks detail 1 View document icon
29 Sep 2015 Drawing Measure document icon Linear park - west general arrangement plan 1 of 3 View document icon
29 Sep 2015 Drawing Measure document icon Primary street commercial square View document icon
29 Sep 2015 Drawing Measure document icon Primary street - amendment to accommodate hills layout View document icon
29 Sep 2015 Drawing Measure document icon Primary street - amendment to accommodate hills layout View document icon
29 Sep 2015 Public Correspondence Measure document icon Letter from aecom requesting minor amendments View document icon
24 Feb 2015 Decision Measure document icon View document icon
24 Feb 2015 Report Measure document icon Committee View document icon
03 Feb 2015 Report Measure document icon Design and access View document icon
29 Jan 2015 Drawing Measure document icon Revised nothern kerb line- alternative bus route swept paths- school square View document icon
29 Jan 2015 Drawing Measure document icon Bus & car swept paths- revised commercial square View document icon
29 Jan 2015 Drawing Measure document icon Bus & pantechnicon swept paths- revised commercial square View document icon
29 Jan 2015 Report Measure document icon Revised movement strategy report View document icon
27 Jan 2015 Drawing Measure document icon Arboricultural implications plan View document icon
27 Jan 2015 Report Measure document icon Revised arboricultural method statement View document icon
27 Jan 2015 Report Measure document icon Revised arboricultural report View document icon
27 Jan 2015 Report Measure document icon Revised design & access statement View document icon
26 Jan 2015 Other Measure document icon Revised drawings index View document icon
26 Jan 2015 Revised Drawing Measure document icon Primary street - general arrangement plan 1 of 3 View document icon
26 Jan 2015 Revised Drawing Measure document icon Street furniture View document icon
26 Jan 2015 Revised Drawing Measure document icon Primary street - community square View document icon
26 Jan 2015 Revised Drawing Measure document icon Primary street - comercial square View document icon
26 Jan 2015 Revised Drawing Measure document icon Greenways west - general arrangement plan View document icon
26 Jan 2015 Revised Drawing Measure document icon Greenways east - general arrangement plan View document icon
26 Jan 2015 Revised Drawing Measure document icon Linear park east - general arrangement plan View document icon
26 Jan 2015 Revised Drawing Measure document icon Linear park central - general arrangemen plan View document icon
26 Jan 2015 Revised Drawing Measure document icon Linear park west - general arrangement plan View document icon
26 Jan 2015 Revised Drawing Measure document icon Primary street - hardworks detail 2 View document icon
26 Jan 2015 Revised Drawing Measure document icon Primary street - general arrangement plan 3 of 3 View document icon
26 Jan 2015 Revised Drawing Measure document icon Primary street - general arrangement plan 2 of 3 View document icon
05 Dec 2014 Other Measure document icon Eia screening letter View document icon
05 Dec 2014 Other Measure document icon Screening option View document icon
05 Dec 2014 Report Measure document icon Surface water strategy View document icon
04 Dec 2014 Other Measure document icon Eia information & link (environmental impact assessment) View document icon
24 Nov 2014 Drawing Measure document icon Linear park - sections a-a,b-b,c-c,d-d View document icon
24 Nov 2014 Drawing Measure document icon Linear park - sections e-e, f-f, g-g, h-h View document icon
24 Nov 2014 Drawing Measure document icon Greenways - sections i-i,j-j,k-k View document icon
24 Nov 2014 Drawing Measure document icon Strategic infrastructure View document icon
24 Nov 2014 Other Measure document icon Appendices - appendix a list View document icon
24 Nov 2014 Drawing Measure document icon Existing drainage catchment plan View document icon
24 Nov 2014 Drawing Measure document icon Surface water strategy & surface water drainage View document icon
24 Nov 2014 Drawing Measure document icon Diverted overhead lines stage 2 View document icon
24 Nov 2014 Drawing Measure document icon Diverted overhead lines stage 3 View document icon
24 Nov 2014 Drawing Measure document icon Diverted overhead lines stage 4 View document icon
24 Nov 2014 Drawing Measure document icon Layout & cross sections View document icon
24 Nov 2014 Drawing Measure document icon Earthworks strategy View document icon
24 Nov 2014 Drawing Measure document icon Typical greenway & swale cross-sections View document icon
24 Nov 2014 Drawing Measure document icon Ground water monitoring View document icon
21 Nov 2014 Report Measure document icon Superceded arboricultural report View document icon
21 Nov 2014 Report Measure document icon Superceded arboricultural method statement View document icon
21 Nov 2014 Report Measure document icon Planning statement View document icon
21 Nov 2014 Other Measure document icon Cil form View document icon
21 Nov 2014 Report Measure document icon Statement of community involvement View document icon
21 Nov 2014 Report Measure document icon Superceded movement strategy report View document icon
21 Nov 2014 Drawing Measure document icon Primary street - hard tree pit detail View document icon
21 Nov 2014 Drawing Measure document icon Primary street - linked hard tree pit detail View document icon
21 Nov 2014 Drawing Measure document icon Primary street - soft tree pit detail View document icon
21 Nov 2014 Drawing Measure document icon Primary street - hardworks detail 1 View document icon
21 Nov 2014 Drawing Measure document icon Primary street - hardworks detail 3 View document icon
21 Nov 2014 Drawing Measure document icon Primary street - hardworks detail 4 View document icon
21 Nov 2014 Drawing Measure document icon Primary street - hardworks detail 5 View document icon
21 Nov 2014 Drawing Measure document icon Primary street - hardworks detail 6 View document icon
21 Nov 2014 Drawing Measure document icon Primary street - hardworks detail 7 View document icon
21 Nov 2014 Drawing Measure document icon Linear park & greenways - indicative parking schedules View document icon
21 Nov 2014 Drawing Measure document icon Linear park - soft tree pit details View document icon
21 Nov 2014 Drawing Measure document icon Typical greenway crossing - primary street View document icon
21 Nov 2014 Report Measure document icon Scheme of enabling infrastructure works View document icon
21 Nov 2014 Report Measure document icon Phased surface water drainage system report View document icon
21 Nov 2014 Report Measure document icon Phased surface water drainage system - existing drainage catchment plan View document icon
21 Nov 2014 Report Measure document icon Phased surface water drainage system - proposed drainage catchment plan View document icon
21 Nov 2014 Report Measure document icon Phased surface water drainage system - surface water strategy layout View document icon
21 Nov 2014 Report Measure document icon Various plans associated with utilities View document icon
21 Nov 2014 Drawing Measure document icon Utilities 8 detailed drawings View document icon
21 Nov 2014 Report Measure document icon Phased surface water drainage system appendix b & c View document icon
21 Nov 2014 Report Measure document icon Phased surface water drainage system appendix d & e View document icon
21 Nov 2014 Drawing Measure document icon Temporary construction access View document icon
21 Nov 2014 Application Form Measure document icon View document icon
21 Nov 2014 Report Measure document icon Design and access statement rm1_part1 View document icon
21 Nov 2014 Report Measure document icon Design and access statement rm1_part2 View document icon
21 Nov 2014 Report Measure document icon Design and access statement rm1_part3 View document icon
21 Nov 2014 Report Measure document icon Design and access statement rm1_part4 View document icon
21 Nov 2014 Report Measure document icon Design and access statement rm1_part5 View document icon
15 May 2014 BackGround Papers Measure document icon Odrp workshop notes View document icon
02 May 2014 BackGround Papers Measure document icon Odrp design review letter View document icon
01 Jan 1900 Report Measure document icon Foul water strategy View document icon